Condensate-stabilisation package moves into close-out.
For an offshore gas development, all equipment in NGLTech’s package scope had been released for shipment by April 2026. The project is in close-out.
Earlier crude-stabilisation equipment (2015), shown for context.
Offshore gas development · Package scope
A precise status, not a larger claim.
NGLTech’s condensate-stabilisation package for an offshore gas development progressed through engineering, procurement, fabrication and testing into shipment release.
By April 2026, all equipment in the NGLTech package scope had been released for shipment. The project is in close-out.
The package illustrates the connection between process engineering and project delivery. A condensate-stabilisation duty has to be translated into a defined process basis, equipment and control requirements, supplier scopes, fabrication deliverables, test records, interfaces and a handover trail that the wider project can use.
We name a client only where that consent is on file.
Package delivery
From process basis to documented handover.
Engineering basis
Translate the operating duty into process, equipment, control, materials and interface requirements.
Procure and fabricate
Coordinate vendors and fabrication against the approved requirements and the package delivery plan.
Test and close out
Capture test, release and documentation status accurately so the next project stage starts from a controlled record.
The wider capability
Engineering that carries through delivery.
See how a package is engineered and delivered, and the kinds of work already completed.
News & Insights
More stories.
NGLTech presented at MENA Wells 2026 in Abu Dhabi
A pre-recorded film and a live, remote Q&A on idle and marginal wells: freeing the barrels that do not need a well intervention.
Read the storyEnhanced LPPU™: a proven platform, built to order
The LPPU platform has three offshore installations across two fields, the first in 2014. The Enhanced LPPU™ carries it forward with the liquid piston, built to order for each well.
Read the storyCapacity means nothing without a stated suction pressure
Why a booster’s headline number is not a screening answer, and what a credible first screen needs instead.
Read the storyStart with the process basis